日立GVF-III調試手冊
日立GVF-III調試手冊
GVF-Ⅲ電梯安裝調試手冊
前 言
本資料介紹 GVF-Ⅲ型電梯,該梯種以集成了變頻控制和邏輯控制的 EV-ECD 01(MCUB)
控制板、SCL 串行通訊系統和 RD-DMS01 變頻門機系統作為電氣的關鍵組成部分,并基本使
用了 GVF-Ⅱ型電梯的機械系統。
資料編寫目的:隨著 GVF-Ⅲ電梯的開發成功,在工程方面需要提供安裝、調試、維
修和保養各項工作的技術說明。本資料是根據 GVF-Ⅲ電梯的技術特點,列出電梯在工程環
節中所需使用的資料,為工程本部編寫 GVF-Ⅲ電梯工程技術資料提供依據。由于 GVF-Ⅲ
電梯在電氣控制原理上與 GVF-Ⅱ電梯有較多的相同點,又基本使用 GVF-Ⅱ電梯的機械系
統,所以本資料對于相同點不再進行敘述,只作出說明“與 XX 電梯保持一致”。
本資料基本內容:
(1) GVF-Ⅲ電梯構成和技術特點。
(2) 安裝部分。電氣回路圖的使用說明;控制柜及轎頂電器箱等重要電氣部分的名
稱、功能介紹;工程大、細線及地線的安裝。
(3) 調試部分。運行前需進行檢查的電梯各項安裝情況,控制柜絕緣測試、低速試
運行、變頻門機的調試運行、層高測定操作、高速運行調試、平層精度調整等。
如有修改意見,請填寫附頁的《GVF-Ⅲ電梯調試手冊改進意見表》(復印有效),傳真
或直接交由工程本部工程技術科以作修改。
目 錄
一.GVF-Ⅲ電梯的技術概述··············································5
1.技術構成及特點··················································5
2.GVF-Ⅱ與 GVF-Ⅲ的簡單比較········································6
2.1 機械部分的不同點············································6
2.2 電氣方面不同部分的簡單比較···································7
3.GVF-Ⅲ電梯的規格················································8
二.GVF-Ⅲ電梯機械部分的安裝···········································8
三.GVF-Ⅲ電梯電氣部分的安裝···········································8
1.電氣回路圖的說明·················································8
1.1 電氣回路圖的類別和內容·······································8
1.2 控制柜對外的接線代號及用途···································9
1.3 電氣回路圖的讀圖方法·········································9
2.電梯電源參數····················································11
3.控制柜概要······················································12
3.1 控制柜尺寸及主要部件的安裝圖·································12
3.2 控制柜內部主要部件的名稱和功能·······························14
4.轎頂電器箱元件布置圖············································15
5.井道內器件、電纜的安裝··········································16
5.1 井道內器件的安裝與接線······································16
5.2 井道內電纜的安裝············································16
6. 廳外召喚箱的安裝、接線及 DIP 開關的設置·························17
7. 接地線作業·····················································17
7.1 控制柜內接地線回路圖········································17
7.2 系統地線敷線圖··············································18
8. 其他敷線························································18
四.運行調試···························································19
1. 運行前準備······················································19
1.1 運行前檢查·····················································19
1.2 控制柜絕緣測試·················································19
1.2.1 準備工作··················································19
標記 處數
1.2.2 測試方法··················································19
1.2.3 各回路絕緣標準阻值········································20
1.3 電壓測試························································21
1.4 混雜電壓檢查····················································21
2. 變頻門機的調整···················································22
2.1 機械調整························································22
2.2 電氣系統介紹····················································24
3. 低速試運行······················································26
3.1 開始低速運行····················································26
3.1.1 通電前準備·················································26
3.1.2 通電低速試運行·············································26
3.2 安全回路的確認··················································27
3.3 變頻門機的門寬自檢測············································27
3.4 變頻門機開關門速度的調整········································27
3.5 變頻門機的故障檢出··············································28
4. 高速試運行前檢查和調整··········································28
5. 高速試運行······················································29
5.1 層高測定························································29
5.1.1 層高測定運行前的確定······································29
5.1.2 層高測定的操作順序········································29
5.2 層高測定前后的軟件確認··········································29
5.3 高速試運行······················································30
5.4 電梯對重配置····················································30
5.5 平層調整························································30
5.6 起動補償調整····················································31
5.7 轎內負荷檢測設置···············································31
6. 起動舒適感調整··················································32
7. 功能確認························································32
五.MCUB 板使用說明····················································33
1. MCUB 板簡介·····················································33
標記 處數
2. 小鍵盤介紹·····················································34
2.1 硬件介紹·······················································34
2.2 一般操作·······················································34
2.3 各狀態解釋·····················································35
六.艾默生變頻器專用操作面板使用說明···································39
1. 操作面板硬件說明················································39
2. 按鍵功能說明···················································39
3. 指示說明························································40
4. 鍵盤操作說明···················································40
七.手持編程(GHP)操作說明············································42
1.手持編程(GHP)硬件說明··········································42
2.按鍵功能說明·····················································43
3.GHP 操作流程簡介················································44
八.故障說明···························································44
1.電梯故障的內部處理方式···········································44
2.電梯故障代碼表···················································45
3.變頻器故障代碼表·················································46